PEWAUKEE, Wis. – American Transmission Co. on Tuesday gained approval from the Public Service Commission of Wisconsin to rebuild a 20-mile, 69,000-volt transmission line in Rock and Walworth counties. The Colley Road-Brick Church Rebuild Project will run from the Colley Road Substation in Beloit to the Brick Church Substation in Walworth. The project also involves construction of the new Tiger Substation near Clinton.

“Much of the line is more than 60 years old and needs improvements to ensure electric reliability in the area,” said Jon Callaway, ATC senior local relations representative.

The project will involve stringing new wires and replacing aging wood transmission poles with new steel poles. The new substation will be constructed on approximately 10 acres of land owned by ATC near Clinton.

Construction is planned to begin during the second half of 2015 to meet an in-service date of spring 2018. The estimated cost of the project is $38.5 million.

###

Note to editors: Additional information including a map is available at atc-projects.com and on the PSC’s website (psc.wi.gov) under docket number 137-CE-171.

American Transmission Co. is a Wisconsin-based company that owns and operates the electric transmission system in portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $3.2 billion to improve the adequacy and reliability of its infrastructure. ATC now is a $3.6 billion company with 9,480 miles of transmission lines and 529 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit our website at http://www.atcllc.com.